ACDB Panel Functional Test Checklist – Comprehensive Guide

An AC Distribution Board (ACDB) panel is the cornerstone of any power distribution system, ensuring reliable control, protection, and monitoring. Before commissioning, a detailed functional test validates that all mechanical, electrical, and safety features work as intended. Drawing on industry best-practices and my hands-on experience inspecting control panels, this guide walks you through a step-by-step checklist—from visual inspections to DC scheme verification—to guarantee your ACDB is ready for safe, efficient operation.

General Panel Information

Before you begin any inspection, record key panel data for traceability and future maintenance:

  1. Identification Details:
    • Serial number, model/type, manufacturer
    • Voltage & current ratings
    • Schematic drawing reference
  2. Circuit References:
    • Class specification codes
    • Cable and breaker tagging consistent with design

These details establish a clear baseline and support quality assurance throughout the panel’s lifecycle.

Mechanical Inspection & Visual Checks

A thorough mechanical check ensures the panel’s physical integrity:

  • Fastening & Structure: Confirm all screws, bolts, and mounting brackets are tight and vibration-resistant.
  • Enclosure Condition: Inspect doors, locks, gaskets, and hinges for proper sealing to prevent dust ingress.
  • Component Labeling: Verify ferrule markings, nameplates, and schematic numbers match approved documentation.
  • Wiring Discipline: Ensure terminals use ring-type lugs on current-carrying conductors, wires are properly crimped, and no sharp bends exist.
  • Accessory Mounting: Check that CT shorting blocks, knobs, and enclosures operate smoothly and are securely attached.

Pro Tip: In my past panel audits, loose ring-lugs were the most common cause of intermittent faults—always double-check crimp quality.

Functional Verification of General Panel Features

Once the mechanics are verified, test basic functions:

  • AC Outlet & Lighting: Confirm power to receptacles and illuminate panel lighting.
  • Limit Switches: Operate door-mounted interlocks to ensure correct open/close feedback.
  • Heater & Thermostat: Energize and verify temperature control to maintain internal humidity.
  • Circuit Breaker Manual Operation: Spring-charge breakers, then manually trip and reset using the push-buttons to check responsiveness.

These steps validate that all user-interface elements and safety interlocks work reliably.

Electrical Operation Assessment

Assess the panel’s automatic functions under live power:

  1. Spring-Charging Motor: Energize to confirm charging mechanism works smoothly.
    • Local/Remote Control: Operate circuit breakers from both local push-buttons and remote control modules.
  2. Emergency Trip: Simulate fault conditions to verify the breaker trips—and that interlocks isolate the correct bus zones.
  3. Indicator Lights: Check ON, OFF, and TRIP LEDs for correct color, brightness, and consistency.

Authoritative Note: IEEE standards recommend clear, separate indicators for each status to minimize operator confusion in urgent scenarios.

Interlock Logic Verification

Interlocks prevent unsafe configurations:

  • Normal Mode: Bus 1 and Bus 2 breakers closed, bus coupler open.
  • Fault Simulation: Introduce overvoltage on one bus—verify that the affected bus isolates automatically.
  • Backfeed Prevention: Ensure logic blocks any closed-loop conditions between multiple sources.

This logic test confirms the panel’s ability to protect equipment and personnel during anomalies.

DC Auxiliary Scheme Check

DC circuits power critical relays and controls:

  • DC MCB Operation: Test miniature circuit breakers under load and no-load conditions.
  • Relay Functional Test: Simulate overcurrent, undervoltage, and overvoltage inputs to verify response.
  • Spring-Charging Motor (DC): Confirm DC-powered spring charging functions identically to AC variant.
  • Auto/Manual Selector: Switch between modes to ensure seamless changeover of auxiliary power sources.

Proper DC scheme verification is vital—these circuits back up main protection functions in emergencies.

ACDB Auxiliary Circuit Inspection

Verify all auxiliary wiring and protective coordination:

  • Cable & Breaker Ratings: Record conductor sizes and breaker amperages; compare against design specs.
  • Route Tracing: Physically trace each auxiliary circuit from source to load to detect miswiring.
  • Label Accuracy: Confirm segment labels match both schematic and physical routing.

Accurate auxiliary wiring guarantees reliable communications between components under all conditions.

Annunciation & Alarm System Check

The annunciator provides early warning of faults:

  • LED Indicators: Test each alarm input—confirm correct LED color (red/yellow) and brightness.
  • Audible Alarms: Engage buzzers, then reset to verify proper latching and reset behavior.
  • Delay Settings: Measure indication delays to ensure they align with design requirements.
  • Terminal Blocks: Inspect wiring at annunciator TBs to confirm secure connections.

Effective alarm testing ensures that operators receive timely, unambiguous fault notifications.

Final Checklist & Documentation

Before handover, complete this summary:

Test CategoryStatus (Pass/Fail)Comments
General Information Recorded
Mechanical & Visual Checks
Functional Panel Features
Electrical Operation
Interlock Logic
DC Scheme Functional Check
ACDB Auxiliary Circuits
Annunciation & Alarm System

Author’s Insights

I’m Aanya, a 21-year-old technical blogger with three years of hands-on writing and practical inspection experience. Having collaborated with electrical maintenance teams and software-driven testing initiatives, I’ve seen first-hand how a structured checklist—like the one above—prevents field failures and ensures safety. My approach blends industry standards with real-world lessons, so you can trust this guide for your next ACDB panel rollout.